California Bullet Train Audit: Expect More Cost Overruns

Let our journalists help you make sense of the noise: Subscribe to the Mother Jones Daily newsletter and get a recap of news that matters.

I know I’m probably trying your patience, but the state auditor’s report of California’s LA-San Francisco bullet train was released on Thursday:

[Elaine] Howle suggested that much of the spending so far may have been an outright waste….The audit, ordered by the Legislature this year, found extensive mismanagement, including serious problems tracking contracts, reviewing invoices for payment and monitoring construction progress….The project is 13 years behind the schedule set in the bond act approved by voters in 2008 and has grown in cost by $44 billion over its original $33-billion price target.

….Shortcomings in the agency’s ability to monitor progress on its existing $5.6 billion of construction, engineering and environmental contracts have been well known to the authority. Howle noted that the authority’s in-house audits in 2014 and 2015 identified those problems but that the authority was unable to implement corrective action….For five years, rail authority executives have told The Times that they recognize a need for bolstering the ranks of state managers and relying less on outside advisors. The authority reiterated a plan to the auditor to rely less on consultants.

Gov. Jerry Brown has been an ironclad supporter of the bullet train, but he leaves office in January and Gavin Newsom will take over. Newsom has been pretty lukewarm about the project, which produces my favorite paragraph in the story:

The 87-page audit gives Newsom the basis for almost any kind of restructuring he would want to make, though support for the train remains high among its key constituencies: construction companies, labor unions and Californians who have traveled by bullet train in Europe or Japan.

Construction companies and labor unions, sure. Of course they support it. But if the best you can dig up for #3 is folks who have traveled on bullet trains once or twice on vacation—well, you’re in trouble, aren’t you?

DOES IT FEEL LIKE POLITICS IS AT A BREAKING POINT?

Headshot of Editor in Chief of Mother Jones, Clara Jeffery

It sure feels that way to me, and here at Mother Jones, we’ve been thinking a lot about what journalism needs to do differently, and how we can have the biggest impact.

We kept coming back to one word: corruption. Democracy and the rule of law being undermined by those with wealth and power for their own gain. So we're launching an ambitious Mother Jones Corruption Project to do deep, time-intensive reporting on systemic corruption, and asking the MoJo community to help crowdfund it.

We aim to hire, build a team, and give them the time and space needed to understand how we got here and how we might get out. We want to dig into the forces and decisions that have allowed massive conflicts of interest, influence peddling, and win-at-all-costs politics to flourish.

It's unlike anything we've done, and we have seed funding to get started, but we're looking to raise $500,000 from readers by July when we'll be making key budgeting decisions—and the more resources we have by then, the deeper we can dig. If our plan sounds good to you, please help kickstart it with a tax-deductible donation today.

Thanks for reading—whether or not you can pitch in today, or ever, I'm glad you're with us.

Signed by Clara Jeffery

Clara Jeffery, Editor-in-Chief

payment methods

We Recommend

Latest